June 2026 construction Update
Momentum remains strong as we head into the height of summer here in Dillon, with excellent progress across the site. In June we:
Completed the level 2 deck with the final pour finishing on 6/29
Poured 24 columns from levels 1-2 and 2-3
Poured the level 2-3 stair core(the rectangular structure that will hold the stair case)
Completed half of the underground waterproofing on the East and North sides
Stay tuned for more as we continue to push forward, but for now you can enjoy this beautiful fly-around of the site.